Terms of Reference (ToR) for Tanzania 200 sqm Mosque,120sqm Classrooms Construction and Borehole Drilling Projects
Project Name : Ahlul Quran
Project N: umber : ECP26058
Location: KIGOMA-KIBIRIZI
Start Date : DECEMBER,2026
End Date : MAY,2027
- Project Overview
This document outlines the Terms of Reference for the Masjid construction project, which includes the design, development, and completion of a Masjid in accordance with approved architectural and engineering plans, as specified by the Africa Relief and Community Development (ARCD). The project will follow all relevant TO Country construction codes and regulations, as well as internationally recognized standards where applicable.
- Objectives
The objective of this ToR is to outline the requirements and expectations for contractors interested in executing the Masjid and classrooms construction project and drilling borehole. The contractor will be responsible for the procurement of materials, site management, construction, and completion of the Masjid, including all architectural, structural, and special features as detailed in the contract agreement.
- Scope of Work
The contractor is expected to:
- General Scope
o The works comprise a 200 sqm Masjid; a 120 sqm building with three classrooms and an office; and an 80-metre borehole fitted with a 3-metre tower and a 5,000-litre storage tank. All works must follow the approved architectural and structural drawings.
o All works shall adhere to Tanzania construction codes and regulations.
2. Foundation and Structural Works
- Excavation for foundations shall be to a 70cm depth specified in the structural drawings, approved by the supervising engineer.
- A blinding layer of concrete (10 cm thick) shall be laid before placing 4 reinforcement bars of 12mm and a beam of 25cmx20cm is made.
- The same size beam is made after foundation wall is complete.
- Reinforcement: Steel rods used must conform to BS 4449:2005 standards (or equivalent).
- Columns footing of 75cmx75cm is made at 30cm below the foundation trench reinforced with 12mm steel bars as specified. Column of 25cm is raised to the superstructure.
- Flooring
o Interior: Ceramic tiles of size 40 cm x 40 cm, minimum thickness 10 mm, to be installed on a levelled and screeded concrete base. Tiles must be slip-resistant and approved by the supervising engineer.
o Exterior Veranda: Non-slip ceramic tiles to be installed, with the floor raised 50 cm above natural ground level, incorporating appropriate drainage systems.
- Walls
o Block walls to be constructed using standard 400mm x 200mm X 150mm blocks (5inches), bonded with mortar of a cement-sand mix ratio of 1:3.
o Walls to be rendered and finished with high-quality paint suitable for humid climates.
5.Roofing
o External roof covering to use 0.45mm thick zinc sheets of “long-span, self-locking” type. Roof pitch to be designed to accommodate heavy rainfall.
o Roof trusses to be constructed using treated timbers.
6.Doors and Windows
o Doors: Metal doors (Turkish design) of specified dimensions. All doors are to be primed and painted with anti-corrosion coatings.
o Masjid Windows: Eight Aluminium-framed windows with burglar-proofing and mosquito netting.
7.Ceiling
o Internal ceiling to be constructed from gypsum boards ensuring a smooth, painted finish.
o Ceiling height to be 3.5m high.
- Toilets
o Construct 8 (eight) toilets (5 for the male and 3 for female) of sizes 1.5m x 1.2m each as per design.
o Wudu area to be next to toilets.
o Windows at 600mm x 600mm.
o Ceiling height to be 2.5m high.
o Install nonslip ceramic tiles.
o Install 6 (six) squatting and 2(two) Sitting toilet(s) and taps in each of the (6) Six toilets.
9.External Works
o Paving blocks 100cm wide to surround the structure.
10.Special Features
o Imam’s pulpit to have 3 steps above finish floor level (10cm thick 250cm wide)
o A fibreboard project billboard (1m x 0.7m) detailing project information to be installed near the entrance.
11.Lighting
o Installation of a lighting system to provide eco-friendly illumination for the Masjid.
Deliverables
The key deliverables for the project include:
- Site preparation, including excavation, leveling, and foundation works. • Construction of the superstructure (columns, walls, roofing).
- Installation of external and internal finishes (flooring, windows, doors, roofing, and lighting system).
- Final inspection, warranty, and project handover with rectification of any defects identified during the final inspection.
Project Timeline
The project is expected to be completed within 4 months, with penalties imposed for delays. A penalty of 1% of the contract value will be charged per week of delay beyond the agreed project timeline.
Contractor Responsibilities
The contractor will be responsible for:
- Procurement of Materials: Ensuring all materials meet the specifications outlined in the contract, including roofing materials (0.45mm zinc sheets), ceramic tiles, steel reinforcements (BS 4449:2005), and concrete.
- Worker Safety: Providing appropriate safety gear for all workers (helmets, gloves, boots) and ensuring compliance with Country labour laws, including worker insurance and fair wages.
- Site Management: Ensuring the safety and security of the construction site, including managing tools and materials to prevent theft, and ensuring proper waste disposal.
- Compliance with Building Codes: Adhering to Country construction codes and international standards (BS, ASTM) for all construction activities.
- Reporting: Submitting photographic and video documentation at each construction stage, with progress reports every two weeks, approved by the supervising engineer.
- Completion: The contractor must complete the project in adherence to the contract timeline, rectify any defects at no additional cost, and submit for inspection and handover upon completion.
ARCD Responsibilities
ARCD will:
- Funding: Provide funding for the project according to the agreed payment schedule.
- Documentation: Supply the approved architectural and structural drawings, technical specifications, and design templates.
- Supervision: Conduct site inspections to ensure compliance with project specifications and approve milestone reports, including progress photos and videos.
Payment Terms
Payments will be made according to the following milestones:
- Advance Payment: 40% upon signing, after submission of performance guarantee.
- Roofing and Shell Completion: 40% after installation of roof structure, roof sheets, windows and doors.
- Finishing Completion: 15% after all plastering, flooring, painting, and external works are completed and approved.
- Final Quality Assurance: 5% after six months, following final inspection and resolution of any reported defects.
Performance and Penalties
The contractor will face penalties for:
- Delays: 1% of the contract value per week beyond the agreed completion date.
- Substandard Work: A penalty of 5% for non-compliance with specifications or substandard materials or workmanship.
- Unauthorized Subcontracting: Immediate termination of the contract and a penalty of 10% of the total contract value for any unauthorized subcontracting.
Documentation Requirements
Interested contractors must provide the following documentation for compliance and evaluation:
- Registration Certificate: A valid, up-to-date registration certificate from the relevant authorities in Country.
- Signed Code of Conduct: A signed copy of the ARCD Code of Conduct.
- Insurance: Proof of insurance for worker safety, public liability, and materials.
- Performance Guarantee: A performance guarantee equivalent to 10% of the contract value.
- Bank Account Information: A bank statement confirming the contractor’s ability to manage funds securely.
- CEO National Identification Number Copy: A copy of the CEO’s valid national identification document for record purposes.
Submission Deadline
Interested contractors must submit their proposals, including the required documentation, no later than 10th December 2026.
Contact Information
For further inquiries or to submit proposals, please contact:
Name: Omar Bhoki
Title: ARCD Engineer.
Phone: +255 693 921 717
E-mail:[email protected]